  • rlp2451 rlp2451 Nov 27, 2012 5:41 PM Flag

    Progress Report Filed on LNG Export Terminal

    Sabine Pass LNG, LP, filed a report at FERC on construction activities for its LNG export terminal, stating that as of the end of October, engineering was 28% complete, procurement was 25.9% complete, and overall project completion is 14.7%. Sabine Pass added that the overall project schedule is progressing ahead of the contractual schedule basis. Early targets for Train 1 substantial completion and Train 2 substantial completion are 43 and 47 months, respectively, against the contractual basis of 49 and 58 months for Train 1 and Train 2.

 